TCC Meetings
June 25, 2021
A project status update was sent to the TCC on June 25, 2021.
June 2021 TCC Update (PDF File)
April 5, 2021
TCC Meeting Summary Official Meeting Minutes (PDF file) The following topics were presented at the meeting:
- Update on work recently completed
- NEPA/404 Preferred Alternative Concurrence Point #3 – Preferred Alternative
- Project Schedule
- Next Steps
January 12, 2021
A project status update was sent to the TCC on January 12, 2021.
January 2021 TCC Update (PDF File)
October 8, 2020
TCC Meeting Summary Official Meeting Minutes (PDF file) The following topics were presented at the meeting:
- Update on work recently completed
- NEPA/404 Preferred Alternative Concurrence – Anticipated February 2021
- Project Schedule
- Next Steps
April 29, 2019
TCC Meeting Summary Official Meeting Minutes (PDF file) The following topics were presented at the meeting:
- Summary of the Public Information Meeting held on March 21, 2019.
- Preferred Alternative discussion
- Selection of Preferred Alternative by TCC
- Next Steps
January 24, 2019
TCC Meeting Summary Official Meeting Minutes (PDF file) The following topics were presented at the meeting:
- General Project Status Since Last TCC Meeting
- Presentation of Alternative Alignments for the North-South Connector between Bruce Road and 159th Street.
- Next Steps
November 4, 2015
TCC Meeting Summary Official Meeting Minutes (PDF file) The following topics were presented at the meeting:
- July 2015 IDOT/FHWA meeting summary
- Discussion of reevaluation of the Preferred Alternative
- The next steps in the process
April 14, 2015
TCC Meeting Summary Official Meeting Minutes (PDF file) The following topics were presented at the meeting:
- A history of the project since its initiation.
- The process by which a Preferred Alternative was selected.
- An update on the status of environmental and design studies.
- The next steps in the process.
April 13, 2012
TCC Meeting Summary Official Meeting Minutes (PDF file)
- An update was provided about the environmental coordination.
- An update was provided regarding refinements to the Preferred Alternative.
- The upcoming schedule was discussed.
May 4, 2011
TCC Meeting Summary Official Meeting Minutes (PDF file)
- An update was provided about the environmental coordination that has been occurring particularly in regard to Hine’s emerald dragonfly studies, special waste, noise, and archaeological studies.
- An update was provided regarding changes that have been made to the Preferred Alternative based on coordination with local agencies and property owners.
May 19, 2009
TCC Meeting Summary Official Meeting Minutes (PDF file)
- An update on the status of the project was presented
- A presentation was made regarding the NEPA/404 Merger Process and where Caton Farm / Bruce Road Project stands within that process.
- The Will County Division of Transportation expressed the Need for promptly selecting a course of action for the project
- The Caton Farm – Oak – Bruce – Middle Alignment was recommended as the Preferred Improvement Plan. See Exhibit
February 13, 2006
TCC Meeting Summary Official Meeting Minutes (PDF file)
- An update on the status of the project was presented to the Committee.
- A presentation was made regarding the NEPA/404 Merger Process and where the Caton Farm/Bruce Road project stands within that process.
- Environmental Concerns and coordination efforts in regard to those concerns were discussed.
- A presentation of the full range of potential River Crossing Corridors and Roadway Approach Alignments was presented and recommendations were made as to which alternatives to carry forward tor further study
- A presentation was made regarding the need for local agency leadership to preserve right-of-way for feasible alignment corridors.
- The anticipated schedule for the remainder of the project was discussed including a time frame for conducting the next public information meeting.
March 16, 2005
TCC Meeting Summary Official Meeting Minutes (PDF file)
- An update on the status of the project was presented to the Committee.
- A presentation was made regarding the Concurrent NEPA/Section 404 Merger Process and where the Caton Farm/Bruce Road project stands within that process.
- A short presentation of the approved Purpose and Need Statement was made to the Committee. Environmental Issues facing the project which include potential endangered species impacts were presented and courses of action were discussed.
- Recommendations were made by the consultant regarding which alignment options to be carried forward to the next Merger Process Concurrence Point.
- A presentation was made regarding the need for local agency leadership to preserve right-of-way for feasible alignment options.
February 26, 2004
TCC Meeting Summary Official Meeting Minutes (PDF file)
February 18, 2003
TCC Meeting Summary Official Meeting Minutes (PDF file) Will County Division of Transportation 16841 W. Laraway Road A presentation of the Traffic Conditions Report was given. Note: this report has been superceded by the Traffic Conditions Report dated 02/06
- The reports conclusions and recommendations were given.
- The TCC voted to drop Option O (Des Plaines River Bridge Only), Option M (Cedar Road) and Option N (Briggs Street and U.S. Route 6).
- Option G (Gougar Road), Option H (I-355 Frontage Road) and Option I (New Alignment between Gougar Road and Cedar Road) will be advanced for further detailed investigation.
September 30, 2002
TCC Meeting Summary Official Meeting Minutes (PDF file) Will County Division of Transportation 16841 W. Laraway Road, 9:30 a.m., September 30, 2002 The Village of Homer Glen, Homer Township and the Village of New Lennox are new additions to the TCC. The consultants involved with this project updated the TCC members on recent activities associated with this project. A summary of the two public information meetings and the Intergovernmental Workshop was presented. The status of the traffic demand forecasting was also presented. It is expected to be completed in November, and presented to the TCC in December. A discussion of inferior alignments was undertaken. It was decided that alignments B, J, K, and L would be removed from further study. It was also determined that a new alignment (N) would be added to the study. Alignment N consists of Bruce Road east to Briggs Street, Briggs Street south of U.S. Route 6, and then east on U.S. Route 6 to 159th Street. An Exhibit was presented at the meeting that shows all of the improvement alternates that are currently under consideration.