  • Will County DOT Letter to TCC – December 11, 2017

    Posted on June 25, 2018 by cfb-study-WordPress in Project Update.

    A letter was sent to the Transportation Corridor Committee (TCC) on December 22, 2017 regarding the reevaluation of the north-south alternatives between Bruce Road and 159th Street (IL Route 7).  The letter can be found at the link below: Official Letter (PDF)  

    Continue Reading...
    Comments Off on Will County DOT Letter to TCC – December 11, 2017
  • Project Update – June 2018

    Posted on June 20, 2018 by cfb-study-WordPress in Uncategorized.

    The County has agreed to reevaluate the north-south alternatives between Bruce Road and 159th Street (IL Route 7).  A public meeting is expected in late 2018/early 2019.

    Continue Reading...
    Comments Off on Project Update – June 2018
  • TCC Meeting – November 4, 2015

    Posted on June 20, 2018 by cfb-study-WordPress in TCC Meeting.

    A Transportation Corridor Committee (TCC) Meeting was held on November 4, 2015. Click here for more information.

    Continue Reading...
    Comments Off on TCC Meeting – November 4, 2015
  • Selection of Preferred Alternative & Impacts of Reevaluating North-South Corridor

    Posted on August 19, 2015 by cfb-study-WordPress in TCC Meeting.

    At the request of the TCC, the County has prepared a memo outlining the decision making process that was followed for selecting the Preferred Alternative as well as a memo detailing how reevaluating the north-south connector roadway would impact the overall cost and schedule of the study. Selection of Preferred Alternative (pdf) Impacts of Reevaluating […]

    Continue Reading...
    Comments Off on Selection of Preferred Alternative & Impacts of Reevaluating North-South Corridor
  • TCC Meeting – April 14, 2015

    Posted on June 10, 2015 by cfb-study-WordPress in TCC Meeting.

    A Transportation Corridor Committee (TCC) Meeting was held on April 14, 2015. Click here for more information.

    Continue Reading...
    Comments Off on TCC Meeting – April 14, 2015
  • Fairmont Neighborhood Meeting

    Posted on January 28, 2014 by cfb-study-WordPress in Public Meeting.

    Caton Farm – Bruce Road Phase I Study Fairmont Neighborhood Meeting – January 28, 2014 The exhibits that were on display from the Fairmont Neighborhood Meeting that was held on January 28, 2014 are now available. Also available is the brochure and comment form. Brochure (English) Brochure (Spanish) Welcome Sign Schedule Average Daily Traffic Study […]

    Continue Reading...
    Comments Off on Fairmont Neighborhood Meeting
  • TCC Meeting – April 13, 2012

    Posted on April 13, 2012 by cfb-study-WordPress in TCC Meeting.

    A Transportation Corridor Committee (TCC) Meeting was held on April 13, 2012. A summary of the meeting has been posted, click here for more information.

    Continue Reading...
    Comments Off on TCC Meeting – April 13, 2012
  • TCC Meeting – May 2011

    Posted on May 4, 2011 by cfb-study-WordPress in TCC Meeting, Uncategorized.

    A Transportation Corridor Committee (TCC) Meeting was held on May 4, 2011. An update was provided about the environmental coordination that has been occurring particularly in regard to Hine’s emerald dragonfly studies, special waste, noise, and archaeological studies. In addition, an update was provided regarding changes that have been made to the Preferred Alternative based […]

    Continue Reading...
    Comments Off on TCC Meeting – May 2011
  • Project Update – July 2009

    Posted on July 16, 2009 by cfb-study-WordPress in Project Update.

    On July 16, 2009 the Will County Board adopted a Resolution In Support of the Caton Farm – Oak – Bruce – Middle Alignment.

    Continue Reading...
    Comments Off on Project Update – July 2009
  • TCC Meeting – June 12, 2009

    Posted on June 12, 2009 by cfb-study-WordPress in TCC Meeting.

    A Transportation Corridor Committee (TCC) Meeting was held on May 19, 2009. A summary of the meeting has been posted, click here for more information. It has been recommended that the Caton Farm – Oak – Bruce – Middle Alignment be selected as the Preferred Improvement Plan. See Exhibit. Detailed engineering and environmental studies will […]

    Continue Reading...
    Comments Off on TCC Meeting – June 12, 2009